Milestones

List view

  • No due date
    0/2 issues closed
  • Overdue by 29 day(s)
    Due by December 1, 2025
    14/21 issues closed
  • S-CORE v0.5 is certifiable. This release acts as a baseline for further improvements. Acceptance Criteria: - All S-CORE v0.5 components have all necessary working products according to the S-CORE software development process. - Component Integration Tests are fully available and passed. - Feature Integration Tests are fully available and passed. - Platform Tests are fully available and passed. - Certifiability is demonstrated though an assessment (but no certification is done). - Release and Config Management documents are finished. - All corresponding tools are certified.

    Due by January 30, 2026
    5/7 issues closed